Water and noise restrictions, electricity-cost protections and another agreement are among the conditions attached to approval.
OKLAHOMA CITY — Oklahoma City approved zoning for a large data-center development Tuesday, but the city cannot issue building permits until the developer and the company that will run it sign an agreement with the city covering commitments to the community.
The City Council approved two Beltline Energy rezoning requests near Interstate 40 and Frisco Road, each by a 6–3 vote. The properties lie north and south of the interstate.
The approved plans require a legally binding community benefits agreement signed by the city, the developer and the eventual operator. Beltline did not publicly identify the operator during Tuesday’s presentation.
“We can’t move forward with a building permit” until the city agrees to the terms, David Box, the developer’s attorney, told the council.
The project was able to proceed despite the city’s data-center moratorium because the two pending rezoning cases were specifically exempted when the council adopted the pause in April.
Mayor David Holt cautioned that the approval should not be taken as a welcome for similar developments throughout the city.
“I do not think that means that Oklahoma City is open for business for data centers,” Holt said.
He also requested a six-month extension of the moratorium, which is scheduled to expire Dec. 31. City Manager Craig Freeman said he planned to bring that proposal to the next council meeting.
Electricity costs and city revenue
Before any building can be occupied, the developer must show that its electricity agreement keeps costs created by the project from being shifted to other Oklahoma City electricity customers.
The plans require evidence of an agreement approved by the Oklahoma Corporation Commission and an initial service commitment of at least 10 years.
The plans also seek to protect city revenue by requiring payments equivalent to certain energy sales taxes and franchise fees if exemptions apply, unless the city and developer negotiate different terms.
Those requirements address two concerns surrounding large data centers: who pays for the electricity infrastructure they need and what revenue the city receives.
Water, noise and roads
Both plans prohibit private groundwater wells, a concern for nearby residents who depend on groundwater.
“I asked them to give up their right to the water beneath their land, and they said yes,” said Councilwoman Katrina Avers, whose Ward 3 includes the properties.
Each property’s plan limits drinking-water use to 75,000 gallons a day unless the city’s utilities director approves a higher amount in writing. That includes water used for restrooms, irrigation, fire protection and limited equipment cooling.
Assistant Utilities Director Josh Morgan described 75,000 gallons a day as comparable to a medium-sized industrial customer’s use.
The plans also limit noise at the property boundary to 55 decibels on a scale commonly used to measure what people hear. Separate limits address low-frequency sound.
Before receiving a building permit, the developer must submit an engineer’s study showing the project would meet the noise requirements. Before a building can be occupied, a second noise survey must demonstrate compliance. The city can require an independent review at the developer’s expense.
Routine testing of backup generators is limited to 10 a.m. to 4 p.m. Monday through Friday, with an exception for emergencies.
The developer must also sign a road maintenance agreement before receiving building permits. The plans identify construction routes on Frisco Road and, for the southern property, NW 23rd Street.
The agreements require road maintenance during construction and replacement of damaged sections of Frisco Road afterward. For the southern property, they also require rebuilding NW 23rd Street between Richland and Frisco roads to city rural-road standards.
Other conditions address landscaping and building appearance. Before each building can be occupied, the developer must provide a plan for taking the data center out of service, including how the property would return to another use.
Another agreement required
The community benefits agreement must address city finances, infrastructure, natural resources, neighborhood quality of life and workforce opportunities. The city can require additional topics.
The plans specifically require the developer to secure the signature of the company that will own, control or operate the facility, even if that company is a tenant or another business using the property.
A designated company employee must also serve as a contact for city officials and residents throughout construction and operation.
Yukon resident David Blankenship questioned why the council would approve the zoning before the community benefits agreement was finished and available for public review. He also raised concerns about the combined effects of multiple proposed data centers in the area.
The city must receive the signed agreement before issuing building permits.