A substation transformer illustrates the infrastructure used to deliver electricity. Oklahoma regulators are weighing when to hear arguments over OG&E’s proposed rules for large electricity customers. Photo: Yoshieslunchbox / Wikimedia Commons / CC BY-SA 4.0. Cropped from original.
October 16, 2026

Who pays when data centers bring their own power? OG&E dispute awaits ruling

OG&E wants a hearing moved to January. Google, commission staff and customer groups want to keep the November date.

OKLAHOMA CITY — Whether data centers should be able to buy electricity from independent generators — and what they would still owe OG&E for using its system — lies behind a scheduling dispute Oklahoma utility regulators took under advisement Wednesday.

Oklahoma Gas and Electric Co. wants to move a Nov. 3 hearing on its proposed rules for large electricity customers to Jan. 12, 2027. Google, Corporation Commission staff and several customer groups oppose the delay.

The commission had not issued a written ruling on OG&E’s scheduling request as of Friday afternoon.

Who pays for the system?

Behind the calendar fight is a question that reaches beyond data centers: How should Oklahoma serve customers that need enormous amounts of electricity without shifting the cost to households and other businesses?

OG&E says customers who buy power elsewhere could still depend on its system while avoiding costs other customers would have to cover.

Google and other supporters say letting customers arrange their own supply could reduce the need for OG&E to build expensive power plants, protecting other customers from those costs.

Under Google’s proposal, a data center could arrange to buy some or all of its power from another generator. OG&E would still deliver the electricity over its system and charge for the services it provides.

The customer would remain an OG&E customer but would not pay the utility for generation supplied through those outside arrangements.

OG&E argues that would amount to allowing customers to choose competing power suppliers, something it says Oklahoma law does not authorize. Google maintains its proposed arrangement is lawful.

OG&E wants lawyers to lay out those arguments in writing before commissioners hear the case.

“The Commissioners deserve to have that analysis before they hear the case, not after.”

The company wrote that in its response to opponents.

The opponents say commissioners can hear the evidence in November and receive legal arguments afterward. They also argue OG&E’s proposed process would give the company an unfair advantage. OG&E denies that and says its request would not prevent anyone from presenting evidence.

“The delay carries real costs,” the opposing groups wrote in their joint objection, arguing that postponement would prolong uncertainty for prospective customers and delay protections for existing customers.

OG&E counters that opponents have not identified a customer who would be harmed by the roughly 10-week delay or a legal deadline it would miss.

An administrative law judge recommended granting the delay Oct. 1. Wednesday’s proceeding before the full commission was about objections to that recommendation.

The groups opposing the delay include AARP, Oklahoma Industrial Energy Consumers, Oklahoma Sustainability Network and the Petroleum Alliance of Oklahoma, along with Google and commission staff.

They agree on keeping the November hearing but differ on how much freedom large customers should have to arrange their own power and what they should still be required to pay.

AARP, for example, supports a power-supply option with financial commitments that protect OG&E’s other customers from having to cover the large customers’ costs. The industrial consumer group supports developing the option in a separate case.

The attorney general’s witnesses proposed another approach: Customers could identify power sources that OG&E could acquire to serve its broader system. OG&E has expressed conditional support for that approach.

Moving the hearing to January also would put it before a changed commission. Commissioner Todd Hiett’s term ends Jan. 11, the day before OG&E’s proposed hearing. The winner of the Nov. 3 election between Republican Brad Boles and Democrat Rhonda Eastman would take Hiett’s place.

Opponents cited that timing in their objections but said they were not asking commissioners to find that OG&E chose the date to obtain a particular commissioner or outcome.

OG&E rejected the suggestion, saying it had helped arrange the November hearing for the current full commission and sought more time after other parties’ proposals raised legal questions.